專案處於執行階段 在幾次規劃會議期間,團隊根據他們對其他專案的了解提出了依賴性和風險。專案經理也收到了公司關於團隊計劃如何以及何時進行驗收測試和培訓活動的問題,專案經理接下來該做什麼?
Correct Answer: B
The question describes a situation where the project is in the execution phase and the team has identified dependencies and risks. Additionally, there are questions about acceptance testing and training activities. This suggests that there are multiple factors that need to be tracked and managed. Option B, which suggests creating a log to track risks, assumptions, issues, and dependencies and establishing a periodic review with the stakeholders, is the most appropriate response. This approach ensures that all important aspects are monitored and managed, and that stakeholders are kept informed, which is a key aspect of effective project management. References: PMBOK Guide, 6th Edition, Section 11.2: Identify Risks