一家活動公司正在為退休基金籌劃年度活動。過去 3 年,該組織一直使用敏捷方法進行活動規劃。在啟動階段,在評估事件可能存在的風險和改進的同時,專案經理使用先前的事件回饋來協助開發風險登記冊。
應該使用哪種儀式來開發這個寄存器?
Correct Answer: B
Retrospective results are the outputs of the retrospective meeting, which is a ceremony that is performed at the end of every sprint or iteration in an agile project. The retrospective meeting is an opportunity for the team to reflect on what went well, what could be improved, and how to implement the improvement actions in the next sprint or iteration. The retrospective results can help the project manager to identify the risks and opportunities for the event planning, and to update the risk register accordingly. 12345 References:
* 1: ProjectManagement.com - Retrospectives
* 2: A Guide To Effective Retrospectives By Project Managers
* 3: Retrospective - BrainBOK
* 4: Retrospective - Lovepmp