There are two interdependent projects: the first project is in execution, and the second one is about to be deployed. The first project has been delayed, which is now affecting the second project due to the sharing of resources. What should the project manager do in this situation?
Correct Answer: C
In multi-project environments with shared resources, delays in one project can impact the performance of another. The best approach is to assess the resource constraints and develop a plan to mitigate the risk. This may involve optimizing current resources, negotiating priorities, or acquiring additional resources (internal or external) based on impact assessment. The PMBOK Guide - Seventh Edition emphasizes adaptive planning and issue resolution. Resource management is a key domain, and addressing interdependencies with actionable planning is a critical project management responsibility. Option A attempts to shift responsibility and may not resolve the bottleneck. Option B is a reactive procurement step without prior analysis. Option D is passive and does not offer a solution. References: PMBOK Guide - Seventh Edition, Planning and Delivery Performance Domains PMI Practice Standard for Resource Management -