A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue. What should the project manager do next?
Correct Answer: D
When working with global teams, effective coordination across time zones is critical. Creating and sharing a time-overlap schedule ensures meetings are scheduled when most team members can participate. This respects geographic constraints and improves attendance and collaboration. Option A is helpful for relationship building but not a direct solution to time zone conflict. Option B lacks a clear action plan. Option C discourages inclusion and may hinder transparency. References: PMBOK Guide - Seventh Edition, Team and Communication Performance Domains Agile Practice Guide, Chapter 4: "Working with Distributed Teams" -