Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project with multiple teams recently transitioned from a predictive approach to agile as requested by the product owner. Midway through implementation, a team member noticed there was no technical capability to support the current business requirement; therefore, the project will need to be reworked and the issue needs to be communicated to all stakeholders. What should the agile project lead have done to avoid this situation?
Correct Answer: A
The agile project lead should have assessed the technical and organizational readiness for the project and identified risks at the beginning of the first iteration. This would have helped to ensure that the project scope, requirements, and deliverables were feasible, realistic, and aligned with the product vision and customer expectations. It would have also enabled the agile project lead to anticipate and mitigate any potential technical or organizational impediments that could affect the project execution and delivery. By performing this assessment and risk identification early in the project, the agile project lead could have avoided the situation where a team member discovered a technical gap midway through implementation that required rework and communication to all stakeholders. References: PMBOK Guide, 6th edition, page 18; Agile Practice Guide, 2017, page 14; PMP Exam Content Outline, 2021, page 12.