Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
A key stakeholder of a project wants to include additional work before completion. What should the project manager do?
Correct Answer: A
Comprehensive and Detailed Explanation: When stakeholders request additional scope during project execution, the project manager should not make unilateral changes. Instead, the proper course is to process the change request through the approved governance or change control process. This ensures alignment with scope, budget, and timeline. References: * PMBOK Guide - Seventh Edition, Performance Domain: Delivery and Governance * Change Control Process per PMI Standards ##############################################