An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country's unique requirements. The expected revenue for the product is the same for each country. Which release strategy should the project manager recommend?
Correct Answer: B
According to the PMBOK Guide, an iterative-based strategy is a release strategy that delivers the product incrementally over multiple iterations, each adding more functionality and value. This strategy allows the project team to obtain early feedback from the customers and stakeholders, and to adapt to changing requirements and priorities. In this scenario, the project manager should recommend an iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country. This will help to meet the specific requirements of each country, and to deliver value faster and more frequently. References: PMBOK Guide, 6th edition, page 19-20. PMP Questions page 515, question 515. PMP Practice Exam, question 4.