A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project. What should the new project manager do next?
Correct Answer: C
Since the final product has already been delivered, the next step is the formal closure of the project. A key activity in project closure includes developing a transition or handover plan to operations, archiving project documents, and completing administrative closure tasks. According to the PMBOK Guide - Seventh Edition, transition planning and documentation are integral to the Close Project or Phase process. Option A skips the necessary transition step. Option B is unnecessary unless there are incomplete deliverables. Option D is useful but not the primary next step. References: PMBOK Guide - Seventh Edition, Delivery and Measurement Performance Domains PMI Closing Process Group Guidelines ##############################################