A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market How should the project manager address this issue?
Correct Answer: A
When a new technology or requirement emerges during the final stages of a project, it's important for the project manager to assess the business value impact of this change. This involves understanding how the change could affect the project's objectives, deliverables, and stakeholders. If the impact is significant, the project manager should review the product roadmap to include any necessary changes. This approach ensures that the project remains aligned with its strategic objectives and stakeholder expectations, while also staying adaptable to changes in the market or technology landscape. References: PMBOKGuide - Sixth Edition, Section 4.3 Direct and Manage Project Work, pg. 89; Section 4.4 Manage Project Knowledge, pg. 98; Section 4.5 Monitor and Control Project Work, pg. 104; Section 4.6 Perform Integrated Change Control, pg. 115.