A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
Correct Answer: D
During execution, any addition to scope must go through the formal change control process. The project manager should initiate a change request for proper evaluation and approval. This ensures that scope, budget, and schedule impacts are assessed before proceeding. According to the PMBOK Guide - Seventh Edition, any changes to the baseline during execution must follow the change control procedures defined in the governance structure. Option A risks scope creep. Option B is helpful but not sufficient as a next step. Option C closes the door without considering the critical nature of the request. References: PMBOK Guide - Seventh Edition, Delivery and Planning Performance Domains PMI Change Control and Governance Guidelines