A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information How should the project manager handle this situation?
Correct Answer: C
Making work visible using kanban boards is a technique that helps to manage the flow of work and identify bottlenecks or impediments. Kanban boards show the status of each work item, the priority, the assignee, and the dependencies. This way, the project manager can monitor the progress of the software development, communicate with the team and the stakeholders, and resolve any issues that arise. Applying lean manufacturing to limit the team's work is not a suitable option, as it does not address the root cause of the delays or impediments. Increasing retrospectives to deliver results fast is not a realistic solution, as it may compromise the quality of the software and the team's morale. Incorporating small batches of work into the project is a good practice for agile projects, but it does not solve the problem of lack of information or communication. References: Project Management Professional Sample Questions, page 10, question 84. [A Guide to the Project Management Body of Knowledge (PMBOK Guide)], Sixth Edition, page 188, section 6.2.2.4. [Agile Practice Guide], page 51, section 4.2.2.