Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members. What should the project manager do?
Correct Answer: A
Comprehensive and Detailed Explanation: In a new team environment, it is important that everyone participates in establishing team norms. A round table approach allows each team member to voice their opinion in a structured way. This improves psychological safety and encourages open participation in future meetings. References: * PMBOK Guide - Seventh Edition, Team Performance Domain * Agile Practice Guide, Chapter on Servant Leadership and Team Empowerment ##############################################