A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unforeseen problems. What should the project manager do next?
Correct Answer: C
In situations where unforeseen problems prevent the planned execution of a project, the project manager should focus on problem-solving and collaboration to keep the project on track. According to the PMBOK Guide, the project manager's responsibilities include engaging with stakeholders to meet project requirements and creating customer satisfaction1. The Professional in Business Analysis Reference Materials also emphasize the importance of collaboration and stakeholder engagement to address issues and find solutions2. Therefore, helping the customer find an alternative location aligns with the project manager's role in facilitating project success and maintaining stakeholder satisfaction. References: * PMBOK Guide - Seventh Edition, Project Management Institute1. * Professional in Business Analysis Reference Materials, PMI2.