A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it. What should the project manager do?
Correct Answer: C
In a hybrid project environment, especially when dealing with strict schedules and budgets, it is crucial to utilize available resources efficiently. Engaging agile-experienced resources through daily video conferencing is a practical approach that allows for real-time collaboration and communication without the need for physical relocation or additional budget allocation. This method supports the agile principle of individuals and interactions over processes and tools, as it fosters team interaction and customer collaboration, which are essential for agile projects. = The answer is verified by the principles found in the PMI's guide to hybrid project management, which emphasizes the importance of communication and collaboration in a virtual or remote setting. The Professional in Business Analysis Reference Materials also support this approach, highlighting the value of leveraging technology to facilitate effective teamwork and project delivery in a hybrid project context123.