A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective. What should the project manager do?
Correct Answer: B
Implementing a requirements traceability matrix (RTM) is the most effective way for the project manager to ensure that each requirement is linked to business and project objectives. An RTM is a tool that maps out the relationship between requirements and project work, ensuring that predetermined project requirements are met and providing a record of any testing, issues, and completed items. This approach helps in keeping the project aligned with its objectives and facilitates the tracking of requirements throughout the project lifecycle123. : = Information on RTMs from Project-Management.com1, PMI.org2, and ProjectManager. com3. Additionally, techniques for linking business analysis plans to organizational strategy as found in the BABOK Guide4.