During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them. What should the project manager do next?
Correct Answer: B
When a dispute arises about deliverable quality, the project manager should first review the contract and the defined acceptance criteria. Acceptance criteria are agreed-upon standards or requirements a deliverable must meet before it is accepted. If the vendor's components fail to meet those criteria, the vendor may be in breach of contract. Per the PMBOK Guide - Seventh Edition, Control Procurements involves verifying if deliverables meet contract requirements, including acceptance criteria. Option A is premature and assumes new terms are needed before confirming the breach. Option C implies negotiation without verifying the original agreement. Option D is an extreme measure and only valid after confirmation and escalation. References: PMBOK Guide - Seventh Edition, Procurement Performance Domain PMI Practice Standard for Project Procurement Management -