A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned. What should the project manager do next?
Correct Answer: B
When a project manager identifies constraints and conditions that will prevent the project from being completed as initially planned, it is crucial to create a contingency plan. A contingency plan is a proactive strategy that describes the course of actions or steps the project manager and team will take to respond to potential issues. This plan can help manage risk that might arise from changes or uncertainties in the project. It is part of the broader risk management process in project management, which also includes identifying, assessing, and prioritizing risks. References: https://www.coursera.org/articles/project-management-lifecycle https://www.pmi.org/learning/library/delayed-projects-schedule-strategy-10148