An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project. Which artifact should the project lead use to ensure that the project benefits have been identified?
Correct Answer: D
In a hybrid project delivery approach, the business case is the artifact that ensures project benefits have been identified. It provides the rationale for the project by outlining the expected business benefits and aligning them with the organization's strategic goals. The business case is developed during the project initiation phase and is used to justify the investment in the project. It includes an analysis of the costs, benefits, risks, and opportunities associated with the project. PMBOK Guide and PMP certification materials which discuss the importance of the business case in project management, particularly in hybrid and other project delivery approaches. The business case is a critical document that supports decision-making processes and ensures that the project aligns with the organization's strategic objectives and delivers the intended benefits.