A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints. What should the project manager do first?
Correct Answer: C
In a hybrid project management approach, especially one involving organizational transformation, it is crucial to first establish a clear direction and understanding of the project's purpose, mission, and vision. This foundational step ensures that all subsequent actions, including sprints, are aligned with the organization's objectives and the transformation goals. It provides a guiding framework for decision-making and prioritization throughout the project lifecycle12. References: PMBOK Guide - Seventh Edition; "Ultimate Guide To Hybrid Project Methodologies & How To Make Them" by The Digital Project Manager1; "Hybrid Project Management: The What, Why, and Hows" by 4PMTI2.