A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements What should the project manager do to resolve this issue?
Correct Answer: C
In a situation where the project team members lack the necessary technical skills for project success, it's crucial for the project manager to take proactive steps to bridge this skill gap. This could involve finding and providing relevant training to the team members. This approach ensures that the team has the necessary competencies to deliver on the project's objectives, even when the customer's requirements are unclear or changing. It's also aligned with the principles of hybrid project management, which emphasize flexibility, continuous learning, and adaptability in the face of change. References: PMBOK Guide - Sixth Edition, Section 9.4 Manage Project Team, pg. 349; Section 9.5 Control Resources, pg. 356.