In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted the import of this machine model. What should the project manager have done to prevent this from happening?
Correct Answer: C
The project manager should have ensured that regulatory compliance, including import regulations for the specific machine model, was considered in the quality management plan. This would involve understanding and adhering to the legal and regulatory requirements that affect the project scope, deliverables, and processes. By integrating regulatory compliance into the quality management plan, the project manager could have anticipated and mitigated the risk of the machine being blocked by customs, thus avoiding delays and potential financial losses. : Project Quality Management According to the PMBOK1 Machinery Regulation: An Essential Guide2 Project Scope Management according to the PMBOK3