A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project. How should the project manager handle this situation?
Correct Answer: D
According to the Project Management Professional (PMP) principles, when transitioning from a predictive to an iterative approach, it's crucial to maintain clear and transparent communication about project requirements and changes. This is often achieved through the use of product and sprint backlogs, which should be well- documented and visible to all team members. If the team is unsure of what needs to be done due to changes requested by the product owner, it indicates that the backlogs may not be adequately maintained or visible to the team. Therefore, the project manager should ensure that these backlogs are properly documented and accessible to the team. References: Project Management Professional (PMP) Certification Handbook, PMBOK Guide (6th Edition), Chapter 3: Project Management Processes for a Project, Section 3.8 Closing Process Group. Professional in Business Analysis (PMI-PBA) Handbook, Chapter 2: Needs Assessment.