Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
A complex, high-value agile project includes sprint demonstrations with the customer every four weeks. Executive management is concerned about the project's progress and wants more frequent updates on the project status. What should the project manager do?
Correct Answer: B
The project manager should prepare a weekly status report and share it with executive management every week to keep them informed of the project's progress and performance. This will help to address their concerns and expectations, as well as to provide them with relevant information for decision making. The status report should include key metrics such as schedule, cost, scope, quality, risks, and issues, as well as any changes or deviations from the baseline. The project manager should also communicate the benefits and value of the agile approach, and how it aligns with the project objectives and customer needs12. References: * A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, Chapter 10.4.3.1, page 387 * Agile Practice Guide, Chapter 3.3, page 37