A company routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones. How can the project manager address this challenge to assure outsourced vendors deliver?
Correct Answer: B
In the context of remote work, especially when unforeseen risks require a shift to remote operations, it is crucial for project managers to adapt their communication and resource management strategies. This ensures that all team members, including outsourced vendors, are aligned and can deliver effectively. Developing a new strategy may involve leveraging technology for virtual meetings, establishing clear communication protocols, and ensuring that all team members have access to necessary resources and information to perform their tasks remotely1. : = Project Management Strategies for Managing Remote Teams - LinkedIn1.