A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members. What should the project manager do?
Correct Answer: C
When there are changes in team composition, especially due to organizational restructuring, a team alignment session is essential to reset expectations, re-establish collaboration norms, clarify scope, and build cohesion. According to the PMBOK Guide (Seventh Edition), project managers should take the lead in fostering team performance and alignment, especially when the team has undergone major transitions. Option A is premature and defeatist; the issue should be explored with the team first. Option B is rigid and dismisses the real concern about feasibility. Option D may follow after alignment but should not be the first step without full team engagement. References: PMBOK Guide - Seventh Edition, Team Performance Domain PMI's Guidelines on Organizational Change and Transition -