Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile. What should the project manager do to initiate the adoption of agile within the company?
Correct Answer: D
The project manager should first assess the organization's culture, readiness, and maturity to adopt agile methods, as well as the nature and complexity of the projects. Based on this assessment, the project manager can then propose the most suitable agile practices and frameworks that can be tailored to the organization's context and needs. This approach will help to ensure a smooth and successful transition to agile, as well as to address any potential resistance or challenges. Organizing agile workshops, requesting training, or advising the PMO manager to continue with predictive approaches are not the best ways to initiate the adoption of agile, as they do not consider the organization's current situation and capabilities. References: 1, 2, 3 * 1: PMI. (2020). A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition. Newtown Square, PA: Project Management Institute, Inc. Chapter 1, Section 1.2.3.2, p. 9. * 2: PMI. (2020). PMP Sample Test Questions (correct answers are bolded). Retrieved from 3 * 3: PMI. (2017). Agile Practice Guide. Newtown Square, PA: Project Management Institute, Inc. Chapter 2, Section 2.1, pp. 13-14.