A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk. Which risk management process should be performed?
Correct Answer: C
When a defect is identified during user acceptance testing that could significantly impact the system's performance, and the project team advises that this defect puts the delivery date at risk, the appropriate risk management process to perform is Plan Risk Responses. This process involves developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks. The aim is to determine how to approach, plan, and execute the risk management activities for a project1. : Plan Risk Responses for Your Projects - Project Management Academy1.