You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure: Based on this diagram, find out the earliest day on which Activity G can be started.
Correct Answer: D
Explanation/Reference: Explanation: The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must all be completed before Activity G can start. Incorrect Answers: A: Day 13 does not account for Activity F since Activity F is also a predecessor to Activity G. B: Day 7 is not a valid answer. C: Day 22 is the earliest Activity G can finish.