Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?
Correct Answer: B
Explanation/Reference: Explanation: Soft logic can be completed in any order without affecting the outcome of the deliverables. Soft logic is also known as preferential logic, preferred logic, and discretionary dependency. It is defined on the basis of knowledge of best practices and standard procedures for the particular application area. Soft logic is defined by the project management team based on well- known practices in a specific desired sequence. Incorrect Answers: A, C, D: These are not valid definitions of soft logic.