Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?
Correct Answer: C
Explanation/Reference:
Explanation:
This is an example of a fragment network. By adapting the network template to the current project and just using a portion of the template, the template is fragmented. A schedule network diagram template is used to speed up the preparation of networks of project activities. It comprises of the whole project, or a portion of the project activity. The various parts or portions of a project schedule network diagram are known as a subnetwork or a fragment network. When projects have related necessities and components, project managers can develop more efficient network diagrams by using the schedule network diagram templates.
Incorrect Answers:
A: Analogous estimates use historical information to predict the cost or duration of the current project.
B: While this term, sometimes, describes a task within the project network diagram that does not connect to other paths, it is not a valid term.
D: Parametric is an estimating technique that uses a parameter, such as $199 per installation, for a group of installation activities.