You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?
Correct Answer: A
Explanation/Reference: Explanation: The project will end on a Wednesday. If the project work commences on a Tuesday, there will be four days to complete in that week. That will bring the project work down to 63 days of remaining work. Each work week counts as five days of work. 63 divided by 5 is 12 work weeks with three days remaining. The 63rd remaining day will complete on a Wednesday. Incorrect Answers: B, C, D: These are not the valid answers.