You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
Correct Answer: A
Explanation/Reference: Explanation: Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent. Incorrect Answers: B: This is the description of the schedule performance index. C: This is not a valid statement about the project performance. D: This is the description of the cost performance index.