Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure?
Correct Answer: C
Explanation/Reference: Explanation: Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period. Incorrect Answers: A, B: These are not valid project management terms. D: Decomposition is the process of breaking down work packages into the activity list.