Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?
Correct Answer: B
Explanation/Reference: Explanation: Quality control activities are not included in the performance report, but are documented in the quality management plan. A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues. Performance reports are used to report some key information as follows: Current status Scheduled activities Significant accomplishment for the period Forecasts Issues Incorrect Answers: A: Current status of risk and issues can be included in the performance report. C: Analysis of past performance can be included in the performance report to make the report more elaborate. D: Work to be completed next can be included in the performance report.