You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?
Correct Answer: A
Explanation/Reference: Explanation: Resource leveling usually increases the overall duration of the project because management restricts the amount of labor which can be utilized in a given time period. Resource leveling heuristics is a prioritization method that allocates inadequate resources to critical path activities first. It is a schedule network analysis technique useful to a schedule that has already been analyzed by the critical path method. It is used when shared or critical essential resources are only available at certain times, in limited quantities, or to keep resource usage at a constant level. It is a technique that resolves resource conflicts by delaying tasks within their slack allowances. Resource leveling is the process in which project teams come across problems when developing their project schedules. If a company has multiple projects running simultaneously that require the same resources, then problems can arise. It can often cause the critical path method to change. Incorrect Answers: B: New resources are not added as part of resource leveling. C: New resources are not added as part of resource leveling. D: Labor remains the same in resource leveling, but their availability decreases.