You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson's Law state about this scenario?
Correct Answer: A
Explanation/Reference: Explanation: Parkinson's Law states that the work will expand to fulfill the time allotted to it. When you allow five percent additional time per activity the work will expand to consume the additional time that has been allotted to the project task. In other words, activities will not be completed early even if there are no errors or risks. Incorrect Answers: B, C, D: These are not the valid definitions of Parkinson's Law.