You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?
Correct Answer: D
Explanation/Reference: Explanation: According to the question, the cost variance of the project is 30, which is a positive figure. A positive value means that cost is less than planned. What is CV? Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budgeted or lower than budgeted. The cost variance is calculated based on the following formula: CV = Earned Value (EV) - Actual Cost (AC) A positive value means that spending is less than budgeted, whereas a negative value indicates that costs are higher than originally planned for the project. Incorrect Answers: A: This result is depicted by viewing the schedule variance (SV), not the CV. B: If the CV is a negative value, it depicts that the costs are higher than planned. C: If the CV is zero, it shows that cost is right on target.