Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?
Correct Answer: A
Explanation/Reference: Explanation: The code of accounts is a hierarchical numbering system that uniquely identifies each deliverable of the WBS and segments the WBS by levels of numbering. Incorrect Answers: B: A chart of accounts is a financial tracking and assignment tool for common deliverables and activities an organization performs for its customers. C: Component numbering is not a valid term for project management. D: Activity linkage sequencing is not a valid project management term.