You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?
Correct Answer: A
Explanation/Reference: Explanation: Schedule data is not an input to the control schedule process. Organizational process assets are the final input to the control schedule process. The inputs of schedule control process are as follows: Project Management Plan Project Schedule Work Performance Integration Organizational Process Assets Incorrect Answers: B: Work performance information is an input to the control schedule process. C: The project management plan is an input to the control schedule process. D: The project schedule is an input to the control schedule process.