You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?
Correct Answer: B
Explanation/Reference: Explanation: Although this appears to be a simple change the project manager must still follow the rules of the project's change control system. Perform Integrated Change Control is the process of reviewing all change requests, approving changes, and controlling changes to the deliverables and organizational process assets in a project. Perform Integrated Change Control has to do with influencing the things that cause change, determining that the change is required or has happened, and managing the change. Incorrect Answers: A: The project change control process not valid as it's the parent of the integrated change control process, which is more accurate for this question. C: Configuration management is the documentation and control of the product's features and functions. D: Communications management is the execution of the communications management plan.