You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?
Correct Answer: D
Explanation/Reference: Explanation: The milestone list is needed as an input to the sequence activities process. Milestones are timeless events in the project schedule that are generally created as a result of phase completion. What is a milestone list? A milestone list provides a sequence of indicators about project progress to date and achievements or goals, which are to be achieved. The milestone list is used in project management as an indication of progress through the achievement of a major project accomplishment. It is a project document that is not part of the project management plan. The list contains all the project milestones along with information indicating whether they are mandatory to achieve or not. Incorrect Answers: A: Activity attributes describe the work, nature of the activity, and required resources for the activity. B: While the activity list is an input to activity sequencing, it is not a document that shows timeless events or the results of activity phases. C: The project scope statement is an input to the activity sequence, but it does not define the end result of activity phases.