Valid PMI-SP Dumps shared by ExamDiscuss.com for Helping Passing PMI-SP Exam! ExamDiscuss.com now offer the newest PMI-SP exam dumps, the ExamDiscuss.com PMI-SP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-SP dumps with Test Engine here:
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?
Correct Answer: D
Explanation/Reference: Explanation: The cost variance is the earned value minus the actual costs. In this project, you have spent less than what the project is worth, so the project has a positive cost variance. Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budgeted or lower than budgeted. The cost variance is calculated based on the following formula: CV = Earned Value (EV) - Actual Cost (AC) A positive value means that spending is less than budgeted, whereas a negative value indicates that costs are higher than originally planned for the project. Incorrect Answers: A: This is the variance at completion for the project. B: -$111,750 is the cost variance of the project. C: There is a cost variance, albeit a positive one.