Valid PMI-SP Dumps shared by ExamDiscuss.com for Helping Passing PMI-SP Exam! ExamDiscuss.com now offer the newest PMI-SP exam dumps, the ExamDiscuss.com PMI-SP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-SP dumps with Test Engine here:
You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?
Correct Answer: B
Explanation/Reference: Explanation: The schedule baseline is the only output of the develop schedule process among these answers. The three other outputs of the Develop Schedule Process are: project schedule, schedule data, and project document updates. Incorrect Answers: A: Work performance information is an input of the Control Schedule process. C: Resource calendars are an input to the Develop Schedule process. D: Activity duration estimates are an output of the Estimate Activity Duration process.