Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?
Correct Answer: D
Explanation/Reference: Explanation: The schedule performance index is earned value divided by planned value. The close the result is to 1, the better the project is performing. B: This is the cost variance formula. C: This is the formula to find schedule variance. A: This is not a valid formula.