Valid PMI-SP Dumps shared by ExamDiscuss.com for Helping Passing PMI-SP Exam! ExamDiscuss.com now offer the newest PMI-SP exam dumps, the ExamDiscuss.com PMI-SP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-SP dumps with Test Engine here:
Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?
Correct Answer: D
Explanation/Reference: Explanation: Andy and his project team are creating the stakeholder management strategy. The goal is to identify a method to gain support through communications for the project. The stakeholder management strategy is an approach to raise the support and decrease negative impacts of stakeholders during the complete project life cycle. It consists of the following essential elements: Key stakeholders who can significantly impact the project Level of participation in the project desired for each identified stakeholder Stakeholder groups and their management Incorrect Answers: A: Stakeholder assessment information is part of the stakeholder register. B: The stakeholder register contains the stakeholder's identification information, assessment information, and stakeholder classification, but not the management strategy. C: The communications management plan defines how and when communication will happen.