You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?
Correct Answer: B
Explanation/Reference: Explanation: The best answer is simply an exception report. An exception report refers and documents the major mistakes, mishaps, and goofs. In other words, it itemizes the important and critically significant piece of documentation that is vital to the proper and effective functioning of a project. It does not document what has gone right, but rather documents what has gone wrong. Incorrect Answers: A: The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule. C: A performance management report is not a valid project management report. D: The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule.