You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?
Correct Answer: B
Explanation/Reference: Explanation: The Project Staffing Management Plan will define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team. The staffing management plan is part of human resources plan. It is a subsidiary plan of the overall project management plan and defines when project team members will be brought onto and released from the project. It describes when and how human resource requirements will be met. Depending upon the needs of the project, it can be formal or informal, highly detailed or broadly framed. The staffing management plan may include the following items: Staff acquisition, resource calendars, staff release plan, training needs, recognition and rewards, compliance, and safety. Incorrect Answers: A: This is not a valid project management plan. C: The communications management plan defines project communication requirements and expectations. D: The project schedule management will define when resources are needed and scheduled, but not how resources are allowed to be released from the project.