Valid PMI-SP Dumps shared by ExamDiscuss.com for Helping Passing PMI-SP Exam! ExamDiscuss.com now offer the newest PMI-SP exam dumps, the ExamDiscuss.com PMI-SP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-SP dumps with Test Engine here:
You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?
Correct Answer: B
Explanation/Reference: Explanation: The milestone list is the best answer. A milestone list provides a sequence of indicators about project progress to date and achievements or goals, which are to be achieved. The milestone list is used in project management as an indication of progress through the achievement of a major project accomplishment. It is a project document that is not part of the project management plan. The list contains all the project milestones along with information indicating whether they are mandatory to achieve or not. Incorrect Answers: A: The scope baseline is a collection of the project scope, the WBS, and the WBS dictionary. C: The project charter is not the best answer for identifying the milestones. D: The project schedule management plan is not the best answer, as the milestone list is the most direct result.