A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work. However, which of the following statements most accurately describes this parametric estimate assumption?
Correct Answer: A
Explanation/Reference: Explanation: When project team workers complete repetitive tasks, efficiency through learning will diminish the overall duration of the project tasks. A parametric estimate is an estimate that uses a parameter to predict the costs of the project, such as cost per network drop or cost per software license. Parametric estimating technique utilizes the statistical relationship that exists between a series of historical data and a particular delineated list of other variables. Incorrect Answers: B, C, D: These are not the valid statements.