Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure: Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?
Correct Answer: B
Explanation/Reference: Explanation: Activity I must finish by Day 22, so that Activity J can start by Day 23. If Activity I finishes later than Day 22, the project will be late. Incorrect Answers: A: Day 20 is the latest Activity I can start. C: Day 17 is the earliest Activity I can start. D: Day 19 is the earliest Activity I can finish.